BP's Big Payouts Amid Other Oil Spill Liability


Offshore oil platforms under construction in Port Fourchon, La., in 2010

Photograph by Saul Loeb/AFP via Getty Images

Offshore oil platforms under construction in Port Fourchon, La., in 2010

2010
April 16

A BP manager overrules an engineer’s decision to use 21 centralizers to secure a drill pipe in the Macondo well; only six are installed.

April 20
BP decides not to run a test that would determine whether cement has properly sealed the well against leaks. That evening, the well erupts. Eleven men die as the Deepwater Horizon rig explodes and catches fire.

June 16
BP agrees voluntarily to put $20 billion into a fund to pay damages under the supervision of settlement expert Kenneth Feinberg.

July 15
BP and the Coast Guard cap the blown-out well, stopping a geyser of oil that spewed more than 4 million barrels of crude into the Gulf of Mexico.

Aug. 10
A panel of federal judges consolidates hundreds of claims tied to the disaster before U.S. District Judge Carl Barbier in New Orleans.

Dec. 15
The U.S. Justice Department sues BP, rig operator Transocean, and cement contractor Halliburton for violating environmental laws.

2011
Jan. 13

The family of Karl Kleppinger reaches the first settlement of a worker-death suit against Transocean.

April 20
BP sues Transocean and Halliburton, claiming that the contractors share responsibility for the Gulf spill.

Nov. 14
Judge Barbier rules that BP must face spill claims filed by Louisiana and Alabama. Eventually Florida, Mississippi, and Texas also sue BP.

2012
Jan. 26

Barbier rules that under its contract with Transocean, BP must “indemnify” the contractor for pollution-related economic claims. A few days later, the judge decides that BP has to cover certain claims against Halliburton as well.

Feb. 26
Barbier delays a civil trial to allow BP and the Plaintiffs’ Steering Committee to continue negotiating a potential settlement of private business claims.

March 2
BP and the plaintiffs announce an estimated $7.8 billion settlement to resolve most private claims for property damage, economic loss, and medical injuries.

August-September
Hurricane Isaac hits the Gulf Coast and reveals continuing oil contamination in coastal waters.

Nov. 15
BP agrees to plead guilty to 12 felony counts and pay $4 billion in criminal fines; the company also agrees to pay an additional $525 million related to securities-law violations.

2013
Jan. 3

Transocean agrees to pay more than $1.4 billion, including a $400 million criminal fine, to settle federal criminal and civil allegations.

Feb. 5
BP increases the estimated cost of its economic-claims settlement by $680 million to $8.5 billion.

March 5
Barbier rejects BP’s challenge to how court-appointed administrator Patrick Juneau is paying business claims. That issue is now before a federal appeals court in New Orleans.

June 1
BP to date has paid out about $25 billion to cover cleanup and damage claims. The company has set aside more than $40 billion for spill liability. The Justice Department is still seeking up to $17.5 billion while the state of Louisiana estimates that BP ultimately will pay “tens of billions” of dollars in additional claims.

Barrett_190
Barrett is an assistant managing editor and senior writer at Bloomberg Businessweek. His new book, Law of the Jungle, which tells the story of the Chevron oil pollution case in Ecuador, will be published by Crown in September 2014.

American Apparel's Future
LIMITED-TIME OFFER SUBSCRIBE NOW

(enter your email)
(enter up to 5 email addresses, separated by commas)

Max 250 characters

 
blog comments powered by Disqus